How to Create a Clear Project Plan
Elizabeth and Richard Larson 10 September, 2004 17:15:12

One of the critical factors for project success is having a well-developed project plan

Here is a six-step approach to creating a project plan. It not only provides a road map for project managers to follow, but also acts as the project manager's premier communications and control tool throughout the project.

  • Step 1: Explain the project plan to key stakeholders and discuss its key components.

    Unfortunately, the "project plan" is one of the most misunderstood terms in project management. Hardly a fixed object, the project plan is a set of living documents that can be expected to change over the life of the project. Like a road map, it provides the direction for the project. And like the traveller, the project manager needs to set the course for the project, which in project management terms means creating the project plan. Just as a driver may encounter road construction or new routes to the final destination, the project manager may need to correct the project course as well.

    A common misconception is that the plan equates to the project time line, which is only one of the components of the plan. The project plan is the major work product from the entire planning process, so it contains all the planning documents. For example, a project plan for constructing a new office building needs to include not only the specifications for the building, the budget and the schedule, but also the risks, quality metrics, environmental impact, and so on.

    Components of the project plan include:

    Baselines: These are sometimes called performance measures because the performance of the entire project is measured against them. They are the project's three approved starting points for scope, schedule and cost. These provide the stakes in the ground, and are used to determine whether or not the project is on track during execution.

    Baseline management plans: These include documentation on how variances will be handled throughout the project.

    Other work products from the planning process: These include plans for risk management, quality, procurement, staffing and communications.

  • Step 2: Define roles and responsibilities.

    Identifying stakeholders - those who have a vested interest in either the project or the project outcome - is challenging and especially difficult on large, risky, high-impact projects. There are likely to be conflicting agendas and requirements among stakeholders, as well as different slants on who needs to be included. For example, the stakeholder list of the city council where a new office building is being constructed could differ from that of an engineering consulting firm. It would certainly include the developer who wants to build the office complex, the engineering firm that will build the office building, citizens who would prefer a city park, consultants to study the environmental impacts, the city council itself, and so on. The engineering firm may have a more limited view. It is important for the project manager to get clarity and agreement on what work needs to be done by whom, as well as which decisions each stakeholder will make.

  • Step 3: Develop a scope statement.

    The scope statement is arguably the most important document in the project plan. It is used to get common agreement among the stakeholders about the project definition. It is the basis for getting the buy-in and agreement from the sponsor and other stakeholders and decreases the chances of miscommunication. This document will most likely grow and change with the life of the project. The scope statement should include: Business need and business problem Project objectives, stating what will occur within the project to solve the business problem Benefits of completing the project, as well as the project justification Project scope, stated as which deliverables will be included and excluded from the project Key milestones, the approach and other components as dictated by the size and nature of the project.

    It can be treated like a contract between the project manager and sponsor, one that can only be changed with sponsor approval.

Featured Whitepaper Sponsors
Market Place
 

Smart SOA World Tour

Discover how SOA can create smarter outcomes for your business.

Attend and learn:

  • How SOA is helping leading companies to become more agile
  • Where you should be applying SOA processes in your company
  • The top SOA implementation mistakes to avoid

Click here for more information.
  • +

    CIO Live Podcast #79: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires Part II 05 October, 2007 06:00:00

    For his new book, The Outsider's Edge: The Making of Self-Made Billionaires, social researcher Brent D Taylor spent four years of intensive research investigating the psychological make-up and backgrounds of some of the world's richest men and women, including IT luminaries Bill Gates, Larry Ellison and Steve Jobs. Taylor discovered that, despite working in different industries and coming from different upbringings, they all have one thing in common -- they are all outsiders.
  • +

    CIO Live Podcast #78: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires 28 September, 2007 17:34:25

    For his new book, The Outsider's Edge: The Making of Self-Made Billionaires, social researcher Brent D Taylor spent four years of intensive research investigating the psychological make-up and backgrounds of some of the world's richest men and women, including IT luminaries Bill Gates, Larry Ellison and Steve Jobs. Taylor discovered that, despite working in different industries and coming from different upbringings, they all have one thing in common -- they are all outsiders.
  • +

    CIO Live Podcast #77: Panasonic Speeds Up Trans-Pacific File Transfers, Part III 21 September, 2007 07:00:00

    Part three in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    CIO Live Podcast #76: Panasonic Speeds Up Trans-Pacific File Transfers, Part II 14 September, 2007 07:00:00

    Part two in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    CIO Live Podcast #75: Panasonic Speeds Up Trans-Pacific File Transfers, Part I 07 September, 2007 07:00:05

    Part one in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    SOA What? Why You Need SOA Governance Framework 04 December, 2008 08:32:00

    Adopting services oriented architecture (SOA) in your enterprise without thinking through IT governance can cause something like the Gold Rush in the 1800s; extreme rates of growth and minimal law and order which produce unexpected outcomes.
  • +

    The Myth of Cloud Computing 04 December, 2008 08:25:00

    Why the rapid spread of virtual technology is becoming a security risk
    Why the rapid spread of virtual technology is becoming a security risk.
  • +

    Who Pushed Vendors Toward Better Security? 04 December, 2008 09:38:00

    Hint: It had something to do with pressure from customers and government agencies, writes Oracle CSO Mary Ann Davidson
    Hint: It had something to do with pressure from customers and government agencies, writes Oracle CSO Mary Ann Davidson.
  • +

    CPO & CISO: A Comprehensive Approach to Information 04 December, 2008 08:42:00

    GE CPO Nuala O'Connor Kelly advocates greater CPO/CISO cooperation to place the right value on information assets.
    GE CPO Nuala O'Connor Kelly advocates greater CPO/CISO cooperation to place the right value on information assets.
  • +

    Security Culture: Americans are Ferengis, Europeans are Vulcans 04 December, 2008 08:32:00

    Lunch table conversations tell a lot about the culture of security in Europe and the US
    Lunch table conversations tell a lot about the culture of security in Europe and the US.
CIO Webcast Innovation #8 - What are the biggest roadblocks to IT's involvement in innovation at your company?
Watch the latest latest edition of CIO Innovation which is now available for download.
Watch the webcast
Sign up to the CIO Innovation update email


CIO Live Podcast #79: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires Part II
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email
Whitepaper

Radicati Market Quadrant 2008 on Corporate Web Security

An Analysis of the Market for Corporate Web Security Solutions, revealing Top Players, Mature Players, Specialists and Trail Blazers. Read on to discover who makes the grade.