It is so easy for project members to deceive themselves and others partly because seemingly watertight methodologies for software estimation and resultant metrics or measures are anything but.
Sue Bushell 07 July, 2006 16:47:57

Related Features
  • +

    Ticked Off at Tick the Box Mentality 04 February, 2008 13:01:15

    Does your executive search firm know the difference between an MIS manager and a CIO, and if it does, can it explain that difference to its corporate clients?
    Does your executive search firm know its MIS managers from its elbow? Does it even know the difference between an MIS manager and a CIO, and if it does, can it explain that difference to its corporate clients?
  • +

    Strategies for Dealing With IT Complexity 24 December, 2007 10:30:47

    Every innovation, every business process improvement, comes with an IT complexity tax that must be paid by CIOs in time, money and sweat. Here are strategies to mitigate the increasing complexity of IT as it enables new business.
    Every innovation, every business process improvement, comes with an IT complexity tax that must be paid by CIOs in time, money and sweat. Here are strategies to mitigate the increasing complexity of IT as it enables new business.
  • +

    When Egos Dare 05 June, 2007 10:17:02

    For some observers and practitioners, the federated model brings the best elements of centralization and decentralization to the IT table. Others aren’t so sure . . .
    The monarch was dead. Demoralized and shaken, the organization spent time mourning for a popular and high-profile CIO who had reigned for many years. Then, with time starting to dull the pain, the young princes began sharpening their knives, sensing their best opportunity in years to seize power
  • +

    Getting Clueful: Five Things CIOs Should Know About Software Requirements 03 April, 2007 12:37:05

    Software requirements documentation was supposed to itemize everything that the application required. But the project was late, the users were unhappy, and the budget spun out of control. Why? Just ask the developers
    Some days, you wish you had telepathy. You just know that your development staff is holding back in some way, but you don't know how to get them to communicate. Is the project in trouble, but they're afraid to tell you?
  • +

    The Meaning of Success 05 February, 2007 13:32:46

    Part 3 of a Three-Part Examination of Project Management Missing Links
    As companies become wiser about recognizing and adopting successful project management approaches, they face the challenge of creating an environment that fosters success — but that means first defining what success means to the organization
Related Stories
  • +

    VoIP disrupts national security efforts 23 June, 2006 07:40:00

    Australian VoIP service providers must keep interception channels open for law enforcement following a legislative review which IT Minister Helen Coonan has endorsed.
  • +

    The seven deadly sins of outsourcing 21 June, 2006 11:41:21

    These are the transgressions that can doom you to outsourcing hell. Here's how to avoid them.
  • +

    How to build a vendor scorecard 21 June, 2006 09:58:09

    Whether new to a company or making a list of your suppliers based on their performance and importance to you, a scorecard will not only help but will be a record to share with colleagues.
  • +

    How top employers keep IT staffers happy 20 June, 2006 11:42:30

    "In some form, our IT group has been around for 50 years," says Jean Delaney Nelson, vice president and CIO at Securian Financial Group. "And we've never laid off an employee."
  • +

    Accept failure, but focus on recovery 08 June, 2006 15:45:27

    Armando Fox believes that, if you can't build fail-proof systems, you should at least build systems that can recover so quickly that service blips become negligible. A Research Associate with the University of California Berkeley's Reliable, Adaptive Distributed systems laboratory (RAD Lab), Fox was one of the leads on the joint Berkeley/Stanford Recovery-Oriented Computing (ROC) Project that investigated techniques for building dependable Internet services that emphasized "recovery from failures rather than failure-avoidance."

KAZ's Thurow says it is important during the planning process to break the entire statement of work (SOW) down into discrete, credibly estimable tasks and then create a bottom-up plan. And since errors in EV stem from estimating error, measurement error and baseline error, reducing these errors helps validity. Never have tasks on the work breakdown structure (WBS) that are so large in scope that you can only guess partial completion from week to week, he advises. And keep an eagle eye out for manipulation.

"The only way to avoid delusion is to manage to small, cumulative deadlines," RNC Global's Dromgold agrees. "The current practice of breaking projects down into small 'doable' parts is okay, except when we then delude ourselves that progress is being made and are baffled when with integrating testing, things don't work.

"We have to have small chunks, integrated and measured progressively for actual delivered outcomes."

It is the only way to ensure your statistics do not lie.

SIDEBAR: Project Stealth

The success of the stealth bomber proves that even the most complex projects can be managed successfully

You just do not get any projects more complex than development of the F1178 stealth bomber, says Amsterdam-based program manager Peter Luiks. Yet his team successfully completed the project with nary a wishful thought.

The secret lay in the way the US Department of Defence laid down its terms of engagement. "The Defence project management [group] sets you constraints and sets you in a way of working where there is only one way possible, and that is first time right," Luiks says.

The project began with the Department of Defence getting the best people in the Western world together (as long as they could get security clearance). Their mission was to build a plane that would be invisible to all current and future radar systems and that would not radiate heat. Those were the preconditions under which the team was to bring their best in innovation to the table.

From there the team devised a document defining the initial scope of work, then refined it into a first scope of work that was checked and triple checked in Washington before being turned into a joint statement of work. That joint statement of work was huge - Luiks says laid out on the floor it would have covered an entire room and been three folders high - so the team then divided the work into phases and defined deliverables.

"Now, every week a progress report came in from staff managers, project managers, division managers and program managers," he says. "And nobody left the buildings until there was a green light given for the progress report. If there was any mismatch in the progress reports, on Saturday people would come back and work it out so Monday everything was back on track."

Luiks says earned value (EV) estimates are never reliable unless you prepare a joint statement of work, which defines the earned value for both parties involved.

"You must predefine the earned value that should come out of the major complex project from both sides, and first have a statement of work. From the statement of work you have to draft a joint statement of work where both parties sign off on milestones and phases of the plan," he says. "Now if in that last document you also co-sign on the earned value of what has to be reached and what will be considered acceptable value, then the problems are fixed."

Most customers do not know where their own earned value desires lie. And Luiks says organizations or business processes should be in total topological alignment.

Communications and visibility for successes demand the right scope of work analysis and a joint statement of work (SOW). The joint SOW must deliver weekly progress reports in the name of transparency. These weekly progress reports must contain the following items:

  • progress made in line with the joint signed SOW

  • budget spend in line with the joint SOW

  • detected potential mismatches, and suggested paths to time and cost recovery

  • concise "what if" scenarios matching progress to reality

  • a clear goal statement for the next week

  • a map of each task, division and project in topology, in order to produce a concise overview of all progress made.

By doing this the contractor has a one-on-one view of successes as well as any scope drift, he says.

SIDEBAR: How to Write a Statement of Work

By Mary Pratt

It's a tricky task that's essential to project success, and it's easier said than done

Statement of work. As straightforward as it sounds, getting one right is no easy task. But nothing is more fundamental to the success of a project. If the statement of work is too vague, too broad or too generic, it can leave room for various interpretations, which can lead to trouble down the road. That's true for an internal project, and it's doubly true when there are vendors involved.

"The failure to properly execute a statement of work is often the reason parties end up in a dispute," says David M Greenberg, an attorney in the technology, media and telecommunications practice group at Greenberg Traurig LLP 's New York office.

To get your project right the first time, follow these guidelines for writing an effective statement of work, or SOW, as it's affectionately called.

Understand what a SOW is. A SOW defines the scope of work required and the time in which it's to be performed. It's "the cornerstone to an agreement", says Nick Scafidi, IT procurement manager at energy supplier National Grid USA. "It sets expectations, deliverables, what's acceptable, the price, the pricing schedule. Without that, it's like saying to a contractor, 'Build me a house', [without] telling him when, what kind or how big."

Know what to include. Bruce Russell, who signed off on numerous SOWs when he was chief operating officer at a software development company, says a good one includes these things:

  • Major deliverables and when they're expected.

  • The tasks that support the deliverables, as well as which side - the hiring company or the service provider - will perform those tasks.

  • The project's governance process, along with how often governing committees will meet.

  • What resources are required for the project, what facilities will be used and whose equipment will be needed, as well as testing requirements.

  • Who will pay which costs and when.

"The statement of work pulls together all the elements at the beginning," says Russell, now an executive professor at Northeastern University's College of Business in Boston. "And the more precise you can make it, the more quantitative, the better."

Define success. A statement of work should clarify for all parties what constitutes success or failure, says Melise Blakeslee, an attorney in the intellectual property, media and technology transactions group at McDermott Will & Emery LLP in Washington.

"You have to adequately describe what the work is and the criteria for how you both [will] agree" that something is successfully completed, says Ruth Anne Guerrero, standards manager at Project Management Institute, and a former IT project manager.

For example, she says, if you expect your vendor to develop user requirements, your SOW should state that the vendor must interview specific user groups and have them approve the requirements before the job is considered done. That defines success better than simply saying: "Vendor will produce user requirements."

The definition of success depends on the project, Guerrero says. IT project leaders need to specify whether successful implementation is defined by speed, response time, ease of use or all three and then quantify them in the SOW.

Don't forget a timetable. Successful implementations can't be defined by the system's speed or responsiveness alone, though. After all, what good is a great application if it takes a decade to build? That's why a SOW needs to include time elements. Guerrero recommends using language that allows some flexibility rather than a fixed date on the calendar. A SOW should specify, for instance, that the end-user requirements are due two months after the contract is signed - wording that still gets the project moving forward while accommodating potential problems such as a delay in signing the contract.

A SOW should also designate specific times for formal reviews, so all involved can confirm that they're on track, says Matt Liberatore, a professor in the department of decision and information technologies and the John F Connelly Chair in management at the College of Commerce and Finance at Villanova University.

Tie payment to milestones. Another key component to keeping work on track is setting specific milestones in the SOW and tying payment to successful completion, Blakeslee says.

When Scafidi writes a SOW, he specifies that payments to vendors are made upon acceptance of key deliverables. He also notes that he will retain a portion of the pay until the vendor proves that all the deliverables work together.

Use language everyone can understand. The IT department and its vendors aren't the only ones using the SOW, Blakeslee says. So don't write it as if only IT people will see it. "It should be understandable to end users, service providers, management and to a judge," she says.

Be specific. Although numerous parties have to understand the statement of work, be precise in describing the project's scope and requirements, Blakeslee says. She has seen documents that set vague goals, such as "will work to the best of their abilities". She compares that to a homeowner hiring a painter with instructions to "use the best effort possible".

Market Place
 

2008 CIO Summit

19th August, 2008 Four Seasons Hotel, Sydney Developed in partnership with CIO Magazine, IDC, INTEP and the CIO Executive Council.

The world of the CIO is extremely complex and diverse. Multiple priorities demand attention and decisions are needed instantly. Individual teams need to be driven towards common goals, and businesses strive to become more mobile, agile and responsive. For CIOs, the challenge never ends.

Every year the CIO Summit identifies what is top of mind for CIOs across Australia and New Zealand, and offers insight for CIO benchmarking and vendor strategic planning alike.

Recent IDC research shows that over 59% of CIO's believe that 'to achieve their business strategies, technology should be used more aggressively than today.'

Join us on August 19th to discover how this is possible with the latest technologies including Virtualisation, Web 2.0, IP Surveillance and Software as a Service (Saas).

Click here for registration.

Click here for more information.

Please email Denyse_Robertson@idg.com.au for further information.

  • +

    CIO Live Podcast #79: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires Part II 05 October, 2007 06:00:00

    For his new book, The Outsider's Edge: The Making of Self-Made Billionaires, social researcher Brent D Taylor spent four years of intensive research investigating the psychological make-up and backgrounds of some of the world's richest men and women, including IT luminaries Bill Gates, Larry Ellison and Steve Jobs. Taylor discovered that, despite working in different industries and coming from different upbringings, they all have one thing in common -- they are all outsiders.
  • +

    CIO Live Podcast #78: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires 28 September, 2007 17:34:25

    For his new book, The Outsider's Edge: The Making of Self-Made Billionaires, social researcher Brent D Taylor spent four years of intensive research investigating the psychological make-up and backgrounds of some of the world's richest men and women, including IT luminaries Bill Gates, Larry Ellison and Steve Jobs. Taylor discovered that, despite working in different industries and coming from different upbringings, they all have one thing in common -- they are all outsiders.
  • +

    CIO Live Podcast #77: Panasonic Speeds Up Trans-Pacific File Transfers, Part III 21 September, 2007 07:00:00

    Part three in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    CIO Live Podcast #76: Panasonic Speeds Up Trans-Pacific File Transfers, Part II 14 September, 2007 07:00:00

    Part two in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    CIO Live Podcast #75: Panasonic Speeds Up Trans-Pacific File Transfers, Part I 07 September, 2007 07:00:05

    Part one in our three-part special report from CIO's sister publication Network World in the US, as Paul Desmond reports from the Network World IT Roadmap Conference in Santa Clara, California. With development teams in the US and Japan, Panasonic needed a more efficient way to move very large files between the two locations. Iben Rodriguez, IT consultant for Panasonic Research and Development, explains how a storage-area network and virtual server technology helped speed up WAN performance.
  • +

    'I have a lost laptop horror story for you' 30 June, 2008 10:08:14

    The devil of identity theft is in the details that follow...
    The devil of identity theft is in the details that follow: Russ Jones tells a tale of woe that isn't particularly dramatic -- or rare -- and yet it's exactly the kind of story that worries me enough to ignore my better judgment and buy identity-theft protection from my insurance provider.
  • +

    SQL attacks lobs onto pro tennis site 02 July, 2008 11:52:19

    Wimbledon perfect time for crook's criminal racket.
    Visitors to the Association of Tennis Professionals Web site have potentially been infected with spyware after apparent lax security allowed a malicious script to be injected across its pages.
  • +

    Hacking tools: A new version of BackTrack helps ethical hackers 30 June, 2008 10:57:21

    BackTrack is the quickest way to get access to hundreds of (legal) hacking tools
    Version 3.0 of BackTrack has been released. BackTrack is a Linux-based distribution dedicated to penetration testing or hacking (depending on how you look at it). It contains more than 300 of the world's most popular open source or freely distributable hacking tools.
  • +

    Japanese military loses data again 02 July, 2008 08:17:21

    Japan's Self Defense Force lost sensitive data on joint US-Japan military exercise
    Japan's Self Defense Force lost sensitive data pertaining to a joint US-Japan military exercise last year, the Ministry of Defense said Tuesday.
  • +

    ACLU, EFF sue US gov't over mobile phone tracking 03 July, 2008 08:37:23

    Two civil liberties groups sue the US Department of Justice over mobile phone tracking
    The American Civil Liberties Union (ACLU) and the Electronic Frontier Foundation (EFF) are asking a federal court to order the US Department of Justice to turn over records about the agency's tracking of mobile phone users.
CIO Webcast Innovation #8 - What are the biggest roadblocks to IT's involvement in innovation at your company?
Watch the latest latest edition of CIO Innovation which is now available for download.
Watch the webcast
Sign up to the CIO Innovation update email


CIO Live Podcast #79: Brent D Taylor, author of The Outsider's Edge: The Making of Self-Made Billionaires Part II
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email
Whitepaper

Using EMC Celerra IP Storage with Vmware Infrastructure 3 over iSCSI and NFS

Learn to tie virtualized computing to virtualized storage, to offer a dynamic set of capabilities within the data centre and create improved performance and system reliability. Discover how best to utilize EMC Celerra in a VMware ESX environment.

Sponsored Links