NBN Co meets 2012 construction target

Four companies are responsible for rolling out the NBN across Australia – Silcar in NSW, Queensland and the ACT; Transfield in Victoria; Syntheo in the NT, SA and WA; and Visionstream in Tasmania.

NBN Co commenced or completed construction on 758,000 premises by the end of 2012 for the National Broadband Network (NBN).

Communications Minister Stephen Conroy announced in August last year that NBN Co was targeting the milestone by the end of 2012.

Construction commenced or was completed on 784,592 premises by the end of last year.

“The National Broadband Network is an ambitious project which requires the efforts of many people working co-operatively towards a common goal. To have achieved our year-end target is both pleasing for all involved and a clear indication that the NBN project is ramping up to full volume rollout,” Mike Quigley, NBN Co’s CEO, said in a statement.

NBN Co classifies construction commencing on premises once it has issued instructions to its contractors for a fibre service access module, which covers around 2000 to 3000 premises.

However, Malcolm Turnbull, shadow minister for communications and broadband, has strongly contested the measurement of construction commenced for the NBN and has called it a “nonsense figure”.

“Now, what the NBN does, and this is I think a deliberate effort to mislead people ... is they use a metric that is used nowhere else in the industry that I've ever heard of, and this is premises in areas where construction has commenced or has been completed...” he told the ABC's PM program in November last year.

“Now there are two metrics that are really relevant. The most relevant one is obviously premises where you have an active service, where you actually are connected and you've got a customer that's paying you good money for that service.

“The second one is what they describe as premises passed, which is when the fibre is going past a premise.”

Four companies are responsible for rolling out the NBN across Australia – Silcar in NSW, Queensland and the ACT; Transfield in Victoria; Syntheo in the NT, SA and WA; and Visionstream in Tasmania.

Contractor work includes designs, physical visits to the sites of pit and pipe infrastructure and rolling out the passive network.

Meeting the next target could prove harder for NBN Co, with the goal of passing 286,000 premises by the end of June this year.

A premise is deemed as 'passed' when customers are able to connect to the NBN.

At a hearing to the Joint Committee on the National Broadband Network in October last year, Quigley said he was confident of meeting the June target. However, he said it is up to the companies rolling out the network to meet that target.

“It is largely in their hands now, and it is the private sector who is doing it. And that is routine, by the way. Very few telcos these days, anywhere in the world, have their own workforces that do this type of work. They do not build the networks themselves,” he said.

Ralph Steffens, chief operating officer at NBN Co, told the hearing a steep ramp-up was required in brownfield sites in order to meet the June target.

“There will be a steep ramp which will then level out and we will have then a sustainable run rate. It is a challenging program – it is a challenging ramp we have ahead of us – but we are confident that all the work is now handed over to the construction partners,” he said.

Follow Stephanie McDonald on Twitter: @stephmcdonald0

Follow Computerworld Australia on Twitter: @ComputerworldAU

Join the CIO Australia group on LinkedIn. The group is open to CIOs, IT Directors, COOs, CTOs and senior IT managers.

More about: ABC, ABC, ACT, Quigley
References show all
Comments are now closed.
Related Coverage
Related Whitepapers
Latest Stories
Community Comments
Tags: Syntheo, Visionstream Australia, Silcar, FSAM, Transfield, nbn co, National Broadband Network (NBN)
Latest Blog Posts
Whitepapers
  • Staying Ahead of the Data Explosion
    The total volume of data being processed and stored by businesses is rising exponentially. IDC has estimated that the size of the "digital universe" will increase 29 fold between 2010 and 2020. Data storage technology has undergone a steady increase in capacity, along with a steady decline in the cost per unit to store information. Unfortunately, data storage capacity is not keeping pace with data growth and necessitating greater intelligence in the storage infrastructure. Read more.
    Learn more »
  • IDC Insight: Saving Time and Money with Savvy Use of Flash in Automated Storage Tiering
    Storage optimisation and Flash technologies are here to stay. There is also no doubt that unprecedented data growth will continue to strain organisations everywhere. Download this IDC whitepaper to learn more about the cost-effective solution that has helped many organisations increase the productivity of their storage resources.
    Learn more »
  • Best Practices to Make BYOD Simple and Secure
    As consumerisation continues to transform IT, organisations are moving quickly to design strategies to allow bring-your-own devices (BYOD). This paper provides IT executives with guidance to develop a complete BYOD strategy which gives people optimal freedom of choice while helping IT adapt to consumerisation - at the same time addressing requirements for security, simplicity and cost reduction. Read now.
    Learn more »
All whitepapers
rhs_login_lockGet exclusive access to Invitation only events CIO, reports & analysis.
Recent comments

Computerworld
ARN
CFO World
CMO