Vic Labor lashed for IT project management

Ombudsman finds audited IT projects failed to meet expectations, delivery timelines and budget

Victorian taxpayers have been slugged an extra $1.44 billion because the previous Labour government mismanaged information and communication (ICT) projects, the ombudsman has found.

Victorian Ombudsman George Brouwer examined 10 major ICT projects which suffered cost overruns under Labor, including the troubled public transport ticketing system myki.

Mr Brouwer found each project failed to meet expectations, delivery timelines and budget.

The original budget for the projects was $1.3 billion but the latest estimates blew this out by another $1.44 billion.

"On average, projects will have more than doubled in cost by the time they are finished," Mr Brouwer said in his report tabled in parliament on Wednesday.

Premier Ted Baillieu stressed that there would be much greater scrutiny of IT projects under his government.

He said big computer projects tended to run the risk of massive cost overruns and he preferred to see such projects handled in more manageable, bite-sized pieces.

"What we need is to have some performance benchmarks along the way so that we know we're getting the results that are expected," he told reporters in Melbourne on Wednesday.

The report found the two largest projects, myki and the hospital IT system HealthSMART, would need almost $600 million more than planned.

Mr Brouwer said there had also been abject waste, with Victoria Police spending $59 million on its crime database Link over four years, only for it to be cancelled.

Victoria Police Deputy Commissioner Kieran Walshe said he had been quite surprised when he heard of the cost issues but defended the decision to scrap the project as the responsible thing to do.

"There were some faults in the original business case," he said.

VicRoads spent $52 million on a licensing system RandL, which had not yet made it past the design phase.

Mr Brouwer said a number of reports over the years had shown significant shortcomings in the government's management of ICT projects but little had been learned.

He said too often, there was a muted acceptance that all ICT projects go wrong.

But he said the figures were significant.

"They represent many foregone hospital beds, trains, teachers, police and child protection workers," he said.

"It is critical that government manages and reins in these costs if it is to achieve better outcomes."

He made 58 recommendations to improve planning and delivery of the projects.

Victorian Opposition Leader Daniel Andrews said he accepted the report's findings.

"I also accept and note the fact the ombudsman makes it clear that these, whilst they were very important projects, they were high risk projects, they were complex projects and many of them are still very high risk and complex projects," he told reporters.

Join the CIO Australia group on LinkedIn. The group is open to CIOs, IT Directors, COOs, CTOs and senior IT managers.

More about: Leader, Leader Computers

Comments

Post new comment

The content of this field is kept private and will not be shown publicly.
Users posting comments agree to the CIO comments policy.
Login or register to link comments to your user profile, or you may also post a comment without being logged in.
Related Coverage
Related Whitepapers
Latest Stories
Community Comments
Tags: project management, victorian government
Latest Blog Posts
Whitepapers
  • Synergy gains sustainable competitive edge with HP printers, services and solutions
    Western Australian electricity retailer Synergy signed a four-year HP Smart Print Services agreement to establish an efficient and sustainable imaging and printing network which reduces waste and the organisation’s environmental footprint, without compromising on quality, reliability or security. Read more.
    Learn more »
  • Six tips for choosing a unified threat management (UTM) solution
    As network security grows more complex, businesses are demanding the simplicity of unified threat management (UTM). Businesses like yours are replacing multiple, outdated and costly appliances from different vendors with a single, reliable UTM solution. The best solutions offer a more powerful way to manage network security today and in the future. UTM also promises to slash your network security management efforts and hardware costs. This whitepaper offers you detailed advice on how to choose the comprehensive unified threat management (UTM) that best suits your business.
    Learn more »
  • IDC MarketScape: Worldwide Business Process Platforms 2011 Vendor Analysis
    Enterprises adopting business process management (BPM) software have wide-ranging needs, from highly dynamic task management to complex, high-volume processing with a focus on straight-through automation and the ability to rapidly detect exceptions. This IDC MarketScape focuses on what we call business process (BP) platforms, which are optimized to support midrange to more complex use cases. Read on.
    Learn more »
All whitepapers
rhs_login_lockGet exclusive access to Invitation only events CIO, reports & analysis.