CIO
Back In Control
Does your project look like it needs a road under construction sign? If so, try these three suggestions and get your projects under control
John Troyer  05 September, 2008 11:19:00

In spite of spending millions of dollars to deploy project management methodologies and tools, executives still sense a lack of control over the projects in their domain.

The CIO servicing the IT needs of a 75,000-user community complains that all he can get is summary-level green, yellow, red status reports and that the only thing he is sure of is that he does not have control.

The department manager responsible for the executive information system at one of the largest companies in the US says: “We keep breaking our projects into smaller and smaller packages to make sure something gets done, and at the end of each quarter we get lots of glowing reports, but I can’t tell what’s actually getting done. How do I get my projects under control?”

Discussing the dismal delivery record coming out of his organization, the CIO of a Fortune 25 company said: “I’ve got 110 people with the title ‘project manager’ and I don’t think I’ve got a real project manager anywhere in the bunch. How do I get my projects under control?”

One of the most common attempts to get projects under control is to break them into discrete smaller projects. Each major deliverable becomes its own project tailored to fit within a monthly, quarterly or semi-annual horizon.

This approach tends to create unnatural gaps between interdependent elements, in much the same way that an ice field connecting two landmasses becomes a dangerous ice floe if it is broken up. The openings squander the momentum toward achieving the target by burdening resources with a constant stop/start cycle. It is like trying to cross a gap in the ice by diving in the water, swimming and climbing onto a series of icebergs while they drift apart and often drift farther from the other side.

New techniques were created to manage the micro-projects along the way. Scrum, the limited-horizon, single-focus, daily-meeting-based, Agile methodology is such an invention. The key advantage a Scrum approach brings is the unchallengeable focus on a specific deliverable.

Just like any methodology, it is easy to find examples of both glowing successes and glaring failures in the Scrum community. And this is not a place to debate the merits either way. But there are two significant drawbacks to the Scrum approach.

First, there is a real risk of investing too much time in Scrum sessions. A good target for communication is 5 percent to 10 percent of the time. A project suffers when communication drops below 5 percent of the time, and the benefits drop off significantly around 9 percent to 10 percent.

Scrum sessions should take 30 minutes, about 6.25 percent of a day, which fits nicely into the optimum model — so far, so good. Theoretically, that should leave just enough time for other reviews and the management reporting that is necessary in an ideal world.

However, it is rare to find team meetings that last only 30 minutes. It is far more common to find the entire daily allotment of 48 minutes (10 percent), if not more, consistently consumed. By the time the coordination, the other the necessary reviews and reports are complete, team efficiency and effectiveness will have dropped significantly into the unproductive zone, squandering the assigned resources.

Secondly, Scrum-based implementations are subject to the same risks already highlighted above. Each iceberg becomes its own little world, drifting away and subject to tactical adjustments.

These tactical adjustments are often the result of environmental shifts like a shift in management, a key decision maker becoming aware of some new buzzword or concept, or economic and political changes. More often than not, these adjustments dilute the strategic impact that the original, overarching project was supposed to deliver.

Two decades of successful project management in IT, capital construction, engineering and aerospace have revealed three keys to getting projects under control: plug leaks, have an idea and go granular.

Plug Leaks

CIOs frustrated by project management pitfalls in Agile methodologies and techniques like Scrum will learn to plug leaks of time and costs that threaten deliverables

Projects are leaky creations. They leak time, money and specifications threatening deliverables. Those leaks have turned project management into a precious commodity. However, in reality, projects are frequently budgeted and tracked at a summary level that allows some significant leakage, both horizontally and vertically.

Horizontal leakage occurs when parallel tasks, similar to or related to their current activities, derail individuals. For example, someone working on authentication gets pulled into a series of meetings that are outside the project scope because he is an expert on enterprise security. Or a developer helps resolve an issue with the platform on which the code he is developing will run. Although these both yield a real value to the enterprise, their projects have experienced a horizontal leak.

Vertical leakage occurs when past or future projects divert resources from their funded project. An example of a forward vertical leak is project personnel taking time to prepare for the next round of funding and budgets, neglecting their currently funded activities.

Backward vertical leaks occur when current project resources are diverted to address leftover issues from previous projects. For example, an integrator diverts his attention to help track down and solve an issue with a package that will affect the reliability of his deliverable. He discovers that problems slipped in because there was no test or QA specified in the previous project plan and he takes the time to work on the remedy.

Both of these vertical leaks are the result of a poor project management methodology. A proper methodology includes pre-project planning and a rigorous test and QA suite before deployment into production. The second example also indicates either a nonexistent or an ineffective “lesson learned” process.

The key to plugging leaks is to clearly define and enforce acceptable ranges of diversion with a simple parameter like: “We believe in teamwork, so you may invest up to 15 minutes outside the scope of your deliverable; any more than that and you will need to refer them somewhere for funding.” That will protect the project from leakage and help the organization recognize and track it.

Comments

Post new comment

Login or register to link comments to your user profile, or you may also post a comment without being logged in.
The content of this field is kept private and will not be shown publicly.
Enter the fully qualified URL, eg. http://www.example.com/
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

More information about formatting options

Additional Resources
Executive Guides
Whitepapers
Zones
Zone logoZones provide focussed content from CIO and leading technology partners.
Newsletter Subscription
Sign up for our CIO newsletters!
RSS Feeds
Syndicate content

HP Data Center Transformation solutions offer practical ways to overcome the energy and capacity limitations, operational vulnerabilities and technology constraints that can plague your data center. Choosing from a portfolio of solutions matched to your business needs, we can help you transform your data center into a business-driven, process-smart and future-ready asset.

Latest on Data Centre

  • +

    Inside Internode's data centre 05 June, 2009 14:39:00

    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
  • +

    HP uses outside air, big fans, 12-foot raised floor to cool servers 03 June, 2009 07:44:00

    It's also cutting data center power use by painting server racks white
    Just off the North Sea coast in the United Kingdom, Hewlett-Packard Co.'s EDS unit has built a data center that largely relies on cold sea air to keep servers chilled and -- by doing so -- cut the center's cooling power needs in half.
  • +

    HP targets the cloud with new hardware 12 June, 2009 08:27:00

    HP offers complete cloud computing package for businesses
    HP has designed a new portfolio of hardware, software, and services, aimed at reducing costs and saving resource, particularly for businesses involved in Web 2.0, cloud and high-performance computing.
  • +

    Defence to spend $700m on ICT reform 05 June, 2009 11:13:00

    Strategic Reform Program report reveals only half of defence IT budget visible to CIO
    Less than half of the annual $1.2 billion spent by Defence on its ICT is visible to its chief information officer, Greg Farr, a new report has revealed.
  • +

    Inside Telstra's Virtualisation Strategy 11 May, 2009 14:12:00

    Need to cut infrastructure costs driving the strategy
    Telstra is increasingly turning to virtualisation as its core strategy to both manage the rising costs of, and growth in, its data centres, according the company’s CIO, John McInerney.
  • +

    Defence to Initiate ICT Reform Program, Expand CIO Role 05 May, 2009 11:56:00

    ERP rollout, data centre consolidation, single architecture all on the cards, according to the Department of Defence’s strategic policy white paper
    The Defence department has signaled a raft of changes to its approach to information technology under a new ICT reform program.

Free Resource Library

Data Centre Assessments

The First step to Optimising

Speeding business innovation

Removing barriers to growth, increasing agility and driving out costs

Assessments: Ammunition for Facts-Based Decision Making
by Richard L. Sawyer, Senior Principal, HP Critical Facilities Services
Download Podcast Download Transcript
 

CIO Summit The New World Order Opportunities and Challenges for CIOs

23rd July 2009
The Westin Sydney


A content-rich networking event where CIOs and senior executives collaborate on business and technology issues ranging from the impact of the economic downturn to the most pressing trends affecting IT in the enterprise.

Register Now

  • +

    New scam email uses Australian Federal Police to gain victims' trust 03 July, 2009 10:49:00

    Fake offers of free AFP monitoring service to stop "cybernetic attacks"
    Cyber criminals have changed tack in their ongoing scam campaign against banks, moving to the use of government agencies to gain the trust of unsuspecting email recipients.
  • +

    AFP hits $6 million identity fraud syndicate 03 July, 2009 08:25:00

    $500,000 of goods per week purchased with fake credit cards
    The Australian Federal Police (AFP) claims to have struck a major blow to a multi-million identity fraud syndicate.
  • +

    5 steps to secure a new PC 30 June, 2009 00:19:00

    Just unwrapped a brand-new PC? Security pros share their secrets for making your system Internet-safe.
    A common misconception is that a shiny new computer is more or less secure because it hasn't yet been exposed to the Internet's sinister underbelly. But the truth is, these machines come out of the box needing scores of patches, some basic security software downloads and the disabling or replacing of items security pros don't typically trust.
  • +

    Facebook simplifies privacy settings, calls them too complex 02 July, 2009 05:48:00

    The social-networking site is also getting ready to let members share content with anyone on the Internet
    Facebook will simplify the way in which it offers privacy options to its users, as it gets ready to give its members for the first time the option to make the content they post on their profiles available to anyone on the Internet.
  • +

    DR a growing concern for A/NZ CIOs: Symantec 02 July, 2009 09:16:00

    Mission critical apps and cost of down-time major drivers
    CIOs in Australia and New Zealand are increasingly getting involved in the disaster recovery planning of their organisations, according to a new survey from Symantec.
Upcoming Industry Events
  • CIO SummitNSW - Sydney | 23/07/2009 | Hosted by CIO Magazine, IDC & the CIO Executive Council
Whitepaper

Yarra Valley Water At Work: Improving Information Flow with Oracle Technology

Find out how Yarra Valley Water have used IT to effectively leverage IT resources across the organisation whilst improving information flow, enabling business change and empowering the knowledge worker. Watch the video now.


CIO Industry Insight Podcast #4: Kerry Stratton, Managing Director of Healthcare, InterSystems
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email