Why Projects Fail: Part One, Wrong Scope
When looking at your project’s scope ask yourself whether you have a problem scope or just a solution scope and the necessary consideration of the bigger picture has been forgone
Jed Simms  19 June, 2007 09:20:00

In 2005 two major organizations were rationalizing their financial systems (having, through mergers, acquisitions and other events ended up with multiple systems). Both of these projects cost over $10 million — not an insubstantial investment.

In both cases the decision was made to minimize the scope of the project so as to minimize the workload, cost and risks. They decided to "take the best existing practice" and make that the new standard for the whole organization.

Had these organizations simplified and rationalized their financial processes beforehand, the overall cost of their projects may have actually gone down while the value of the benefits would have increased exponentially

Neither project had a realistic business case. One decided to forgo a formal business case and just focus on realizing the identified savings (mainly software licence and consolidation workload savings). The other did follow the business case process but closer scrutiny of the numbers showed that 25 percent of the "benefits" were invalid.

Both organizations, after their project's completion, wished they had not minimized the scope and had "done the job properly".

They found they were still stuck with the same inefficient processes they had before, but had now spent millions of dollars reinforcing them into the business. The opportunities to reduce the time to do processes, to reduce accounts outstanding and other savings had been forgone and, as the new systems were designed to the old paradigm, were too expensive to be gained after the systems' implementation.

A driving force for minimizing the scope is the desire to reduce the project's costs and risks. This is a very narrow way of thinking as the true focus should be on the net value and its achievability.

Systems are automated processes. If you simplify your processes you can often eliminate 50 percent of the process steps. This translates, in our experience, a 20 percent reduction in the overall project implementation costs. So, had these organizations simplified and rationalized their financial processes beforehand, the overall cost of their projects may have actually gone down while the value of the benefits would have increased exponentially. So, minimizing the scope up front is often a false economy and can cause projects to fail.

This led us to define the need for two types of scope — problem and solution scope.

In our example, the starting point should be to take into consideration all financial processes and related systems to define how you want to manage your finances in the future — in process terms. This is your problem scope. It allows you to take a broad perspective to see where the most value is.

The simplification of these processes should be driven by the organization's improvement targets — eg a two-day end of month, halving the accounts receivable amount, halving the accounts payable processing workload.

So then, the project team works with the organization to define the new financial processes and where the systems can add the most value. Just because you have defined the whole end-to-end financial process flows it does not necessitate that you have to implement every idea and improvement.

Done properly, the process simplification step will also identify where the most benefits are, the dependencies involved and the scale of the workload. This allows you select the areas where you want to move forward — your solution scope.

(Obviously, over time, a series of solutions scopes can cover all of the problem scope solution, delivering all of the potential benefits.) Now the solution scope can be used to develop and install a solution within the context of the overall problem scope solution (allowing the necessary hooks and allowances to be made for future needs — increasing future benefits' value).

The decision as to which elements go into the solution scope will be determined by the organization's needs and imperatives - fast savings, system decommissioning needs, problem operational areas, and so on.

Also, why elements are not in the defined solution scope will now be known.

Project manager take away

When looking at your project's scope ask yourself whether you have a problem scope or just a solution scope and the necessary consideration of the bigger picture has been forgone.

The objective of the scope definition is to both control the workload (and associated cost and risks) and maximize the available value. The wrong scope can cut off significant value too soon without knowing that this is what is being done.

In one of the financial systems rationalizations above we quickly computed that a 10 percent increase in project cost would at least have doubled the potential benefits. This additional $20m in benefits was missed. An expensive scope decision.

To read part two of Jed's first column, Why Projects Fail: Part Two, Poor Business Requirements, click here

Jed Simms is CIO magazine's weekly project management columnist. Simms, founder of projects and benefits delivery research firm Capability Management, is also the developer of specialized project management and project governance Web site www.project-sponsor.com

Comments

When projects go bad

We are currently researching real world stories of what goes wrong on projects and think this article contains the sort of good case studies we want to hear.

If there are fellow project managers out there who would like to share their own experiences and knowledge they should visit http://www.whenprojectsgobad.com

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

More information about formatting options

Enter the fully qualified URL, eg. http://www.example.com/
Users posting comments agree to the CIO comments policy.
Login or register to link comments to your user profile, or you may also post a comment without being logged in.
Newsletters
Sign up for our CIO newsletters!
Syndicate content

URL
www.kyoceramita.com.au

Call us on
Australia: 1800 339 003
New Zealand: 0508 596 2732

Email us
marketing@kyoceramita.com.au

Did you realise that the cost or running a laser printer over its lifetime is likely to exceed the original purchase price by several times? To compare your current printer's running costwith a Kyocera printer, select the TCO Calculator

Total Cost of Ownership (TCO)
Kyocera Saves... Try our Saving Estimator now
Calculate Now

Testimonials

 

Wondering how to improve your business with UC on an IP Network?

Join Computerworld's Live Webinar where we will address the move many companies are making towards IP based voice services (SIP trunking, VoIP) and look at how they are using a single connection for data and voice rather than separate lines. Learn about the latest in IP networks and how it can help your organisation.

Wednesday 25th November 2009, Time 10.30 am EST (Sydney, Australia) Screening at your desk

Register now

  • +

    CA brings SOA security to open source JBoss 09 February, 2010 10:08:00

    More commercial options for widely-used app server
    CA has announced its SiteMinder and SOA Security Manager products are now available for the open source JBoss middleware platform.
  • +

    Indian pleads guilty in overseas stock hacking scheme 08 February, 2010 07:50:00

    The group of hackers compromised brokerage accounts, then pumped up the prices of stocks
    An Indian national pleaded guilty Friday to conspiracy and aggravated identity-theft charges related to an international fraud scheme to hack into online brokerage accounts in the U.S. and use them to manipulate stock prices, the U.S. Department of Justice said.
  • +

    E-mail scam steals €3 million in carbon credits 05 February, 2010 06:47:00

    The phishing scheme resulted in losses of up to €3 million from companies
    A clever phishing scheme launched last week may have stolen more than €3 million (US$4.1 million) worth of carbon emission permits from companies.
  • +

    Windows 7 Tips: Best Security Features 04 February, 2010 04:52:00

    IT can specify which applications can run on employees' desktops
    For both enterprises and consumers, one of the big draws of Windows 7 has been its tighter security features.
  • +

    Twitter forces password reset to protect some accounts 04 February, 2010 05:48:00

    The company has discovered that log-in information has been stolen in compromised torrent file-sharing sites
    Twitter required some users to reset their passwords on Tuesday after discovering that their log-in information may have been harvested via security-compromised torrent Web sites, the company said.

Upcoming Industry Events
  • No upcoming events available
Whitepaper

Overtaken by Events? The Quest for Operational Responsiveness | A Survey of Global Energy, Telecoms, and Logistics Businesses

As this white paper will demonstrate, harnessing business events, smart interpretation and fast response are definite objectives, and the need is immediate. Read notes from 400 interviews performed by an independent research company - download now.

CIO Industry Insight Podcast #6: Brenton Smith, Managing Director, CA (ANZ)
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email
Whitepaper
Securing People and Information: How to Protect Against Today’s Web-based Threats

This white paper explores the benefits of an Application Delivery Network, highlighting the ability to protect your users and applications and still deliver outstanding application performance with confidence, consistency and cost-effectiveness across your distributed network.

Read Whitepaper

Brought to you by