Critical.
Authoritative.
Strategic.
Subscribe to CIO Magazine »

UK government CIOs agree action plan for failing IT projects

"Right of intervention" established to deliver successful IT-enabled business change

The U.K. government's CIO Council has agreed a procedure to intervene in major public sector IT projects where whistleblowers raise concerns.

The "right of intervention" has been established in response to a report by the Commons Public Accounts Committee on delivering successful IT-enabled business change.

In separate inquiries, the powerful Commons committee has also highlighted the failure of senior civil servants to call a halt to schemes that were heading for disaster, such as the Rural Payment Agency's project to implement single payments for farmers, which ended in fiasco.

The committee's report on IT-enabled change projects had warned of weaknesses in the way public sector IT projects are managed and monitored. It said the role of the CIO Council -- made up of IT leaders from all major government departments -- was "not yet clear" but urged that it had the "potential to identify key risks to the delivery of programs."

The MPs also argued that the Treasury's new Major Projects Review Group (MPRG) would need "well-rehearsed action plans to intervene to stop programs and projects that begin to falter". Neither the Office of Government Commerce (OGC) nor the Cabinet Office's delivery and transformation group have had powers to halt failing programs, they noted.

In its response to the committee, the government has agreed that the MPRG should "make it clear to departmental project owners what they need to do to address its concerns".

It adds: "The Government CIO and the CIO Council have agreed an intervention process where a program is failing. This intervention process is via the departmental CIO whose responsibility it is to ensure that any action plans are implemented."

The CIO Council have also agreed a "Right of Intervention" to allow "anyone with a concern or issue about a project or program to intervene via the departmental CIO", the response paper says.

Over the next three months, OGC and the Cabinet Office's transformational government team would develop plans with central government departments "to ensure there is tougher scrutiny of all the government's most complex projects and programs and much earlier remedial action where there are signs of failure", the response document promises.

The government has also moved to address the committee's criticism of lack of liaison between the senior responsible owners of major IT projects and ministers. More than a fifth of the owners of mission-critical IT-enabled projects had not met with the relevant minister, while 28 percent met ministers less than once a quarter.

Government CIO John Suffolk has now introduced quarterly reporting of a "pan-government portfolio" of IT-enabled business change programs. The quarterly reports are aimed at identifying and addressing generic issues and risks and for project-specific issues -- and departmental delivery capabilities -- to be "discussed and addressed at ministerial level", the response paper says.

Join the CIO Australia group on LinkedIn. The group is open to CIOs, IT Directors, COOs, CTOs and senior IT managers.

More about: CIO Council, Office of Government Commerce, VIA

Comments

Post new comment

The content of this field is kept private and will not be shown publicly.
Users posting comments agree to the CIO comments policy.
Login or register to link comments to your user profile, or you may also post a comment without being logged in.
Related Whitepapers
Latest Stories
Community Comments
Latest Blog Posts
Whitepapers
  • Protecting Generation Web
    From data privacy to personal safety issues, cyber-bullying, inappropriate content and malware, schools are facing an increasingly difficult task when it comes to allowing young people to spread their online wings without compromising their safety and personal development. The reality that most schools are catering to the needs of mixed age groups and abilities, and it’s easy to understand why a simple stop and block approach won’t work. Learning environments are, by nature, flexible. It stands to reason that the IT resources used in them should be flexible too. Read on.
    Learn more »
  • Enterprise Buyers Guide for Tablets
    In this enterprise buyers guide Computerworld provides a framework for assessing the suitability of tablet computers with different work styles and demands. The guide takes into account upgrade cycles, pricing and contract issues with telecommunications providers. It features a shopping checklist covering screen types, connectivity and hardware as well as a guide to application management. This is in addition to a full roundup of the major players including road maps for the most popular operating systems.
    Learn more »
  • Oracle Database 11g for Data Warehousing and Business Intelligence
    Oracle Database 11g is a comprehensive database platform for data warehousing and business intelligence that combines industry-leading scalability and performance, deeply integrated analytics, and embedded integration and data-quality -- all in a single platform running on a reliable, low-cost grid infrastructure. Read on.
    Learn more »
All whitepapers
rhs_login_lockGet exclusive access to Invitation only events CIO, reports & analysis.
Recent comments