Data Centre Hot Spots Put IT Managers on the Spot
Even if an IT facility has ample cooling capacity, it could still have heat problems if equipment isn't properly arranged. High-density systems such as blade servers are particularly vulnerable to airflow problems
Patrick Thibodeau (Computerworld (US))  29 May, 2007 11:17:55

When Roger Hardy, IT director for the US city of Jeffersonville, gets an alert from an automated monitoring system that his data centre air conditioning is failing, he has 20 minutes to fix the system before the computer room's temperature reaches what he describes as its "death point".

If the thermometer inside the data centre hits 91 degrees, Jeffersonville's IT equipment is cooked — literally. That's what happened this month when the city lost $US20,000 worth of equipment after its strained air conditioning system shut down during a spell of warm weather.

Hardy, who is the sole IT worker for the community of about 29,000 residents, was getting the approval of city officials this week for adding more chiller capacity. That wasn't an IT problem he expected when he took the job in Jeffersonville last December, since the city built a new data centre just last year.

But Hardy's predecessor died very early in the project. And later construction decisions didn't fully account for future cooling needs, Hardy said, adding that it wasn't until after he was hired that he discovered that the new computer room had only a fraction of the required cooling capacity.

To try to avoid unpleasant surprises like the one that occurred in Jeffersonville, IT managers are increasingly investing in computer-aided studies that map the airflow in data centres — similar to the computational fluid dynamics studies that automotive or aircraft manufacturers use to see how air moves around objects.

Even if an IT facility has ample cooling capacity, it could still have heat problems if equipment isn't properly arranged. High-density systems such as blade servers are particularly vulnerable to airflow problems.

But airflow studies can cost as much as $US150,000, said Mark Evanko, president and principal engineer at US-based Bruns-Pak, which conducts computational fluid dynamics studies as part of its data centre engineering and design services.

The studies can be complicated, Evanko said. Assembling the data for a computerized model can involve going from rack to rack and verifying every aspect of airflow in a data centre, he said. The modelling also has to be able to account for possible changes in a data centre's configuration.

Question of effectiveness

In addition, there is debate about how effective the computational fluid dynamics studies are within data centres. Studies of airflow "look good", said John Musilli, a data centre operations manager at Intel. "But at the end of the day, it only works when you have a pristine design."

Musilli, who also is a member of the Data Centre Institute think tank within the US AFCOM professional association for data centre managers, said that as soon as users begin adding equipment to data centres or moving systems around, it creates turbulence that can upset the airflow models.

Intel does use computational modelling in its data centres, but Musilli said that it is just one tool. The models "will tell you if you have a big problem", he said. But they can show large, ominous-looking red areas over racks of servers that upon closer inspection "may not be significant", according to Musilli.

Heat-related server problems may be obvious in some cases but less so in others. For instance, sporadic disk-drive failures may be attributable to normal mechanical problems and not necessarily to hot spots in data centres.

But Bob Sullivan, an engineer and consultant at The US-based Uptime Institute, said he believes that excessive heat is at the root of many IT equipment problems. "The problem is larger than people think," he suggested.

The Uptime Institute looked at 30 computer rooms totalling 27,871 square metres of data centre space and found that on average, 10 percent of the server cabinets had hot spots — areas around them where the temperature was 25 degrees Celsius or higher.

Sullivan said IT managers can do a lot to control the hot-spot problem by placing thermometer strips on their IT equipment, checking them regularly and taking action if temperatures are rising.

Mark Levin, an independent consultant at US-based Metrics Based Assessments, said that although data on heat-related system failures is lacking, he has seen evidence that IT managers are scrambling to cope with the problem.

The need to do something is often apparent when Levin tours data centres. "When you walk through a data centre and can feel the hot spots, you know there is a problem," he said.

Hardy hopes to increase the cooling capacity in Jeffersonville's data centre within the next two months. But until that happens, he said, "it's going to be a rough road and a few late nights".

More about HIS Limited, Intel

Comments

Post new comment

Login or register to link comments to your user profile, or you may also post a comment without being logged in.
The content of this field is kept private and will not be shown publicly.
Enter the fully qualified URL, eg. http://www.example.com/
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

More information about formatting options

Additional Resources
Executive Guides
Whitepapers
Zones
Zone logoZones provide focussed content from CIO and leading technology partners.
Newsletter Subscription
Sign up for our CIO newsletters!
RSS Feeds
Syndicate content Syndicate content

HP Data Center Transformation solutions offer practical ways to overcome the energy and capacity limitations, operational vulnerabilities and technology constraints that can plague your data center. Choosing from a portfolio of solutions matched to your business needs, we can help you transform your data center into a business-driven, process-smart and future-ready asset.

Latest on Data Centre

  • +

    Inside Internode's data centre 05 June, 2009 14:39:00

    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
  • +

    HP uses outside air, big fans, 12-foot raised floor to cool servers 03 June, 2009 07:44:00

    It's also cutting data center power use by painting server racks white
    Just off the North Sea coast in the United Kingdom, Hewlett-Packard Co.'s EDS unit has built a data center that largely relies on cold sea air to keep servers chilled and -- by doing so -- cut the center's cooling power needs in half.
  • +

    HP targets the cloud with new hardware 12 June, 2009 08:27:00

    HP offers complete cloud computing package for businesses
    HP has designed a new portfolio of hardware, software, and services, aimed at reducing costs and saving resource, particularly for businesses involved in Web 2.0, cloud and high-performance computing.
  • +

    Defence to spend $700m on ICT reform 05 June, 2009 11:13:00

    Strategic Reform Program report reveals only half of defence IT budget visible to CIO
    Less than half of the annual $1.2 billion spent by Defence on its ICT is visible to its chief information officer, Greg Farr, a new report has revealed.
  • +

    Inside Telstra's Virtualisation Strategy 11 May, 2009 14:12:00

    Need to cut infrastructure costs driving the strategy
    Telstra is increasingly turning to virtualisation as its core strategy to both manage the rising costs of, and growth in, its data centres, according the company’s CIO, John McInerney.
  • +

    Defence to Initiate ICT Reform Program, Expand CIO Role 05 May, 2009 11:56:00

    ERP rollout, data centre consolidation, single architecture all on the cards, according to the Department of Defence’s strategic policy white paper
    The Defence department has signaled a raft of changes to its approach to information technology under a new ICT reform program.

Free Resource Library

Data Centre Assessments

The First step to Optimising

Speeding business innovation

Removing barriers to growth, increasing agility and driving out costs

Assessments: Ammunition for Facts-Based Decision Making
by Richard L. Sawyer, Senior Principal, HP Critical Facilities Services
Download Podcast Download Transcript
 

CIO Summit The New World Order Opportunities and Challenges for CIOs

23rd July 2009
The Westin Sydney


A content-rich networking event where CIOs and senior executives collaborate on business and technology issues ranging from the impact of the economic downturn to the most pressing trends affecting IT in the enterprise.

Register Now

  • +

    New scam email uses Australian Federal Police to gain victims' trust 03 July, 2009 10:49:00

    Fake offers of free AFP monitoring service to stop "cybernetic attacks"
    Cyber criminals have changed tack in their ongoing scam campaign against banks, moving to the use of government agencies to gain the trust of unsuspecting email recipients.
  • +

    AFP hits $6 million identity fraud syndicate 03 July, 2009 08:25:00

    $500,000 of goods per week purchased with fake credit cards
    The Australian Federal Police (AFP) claims to have struck a major blow to a multi-million identity fraud syndicate.
  • +

    5 steps to secure a new PC 30 June, 2009 00:19:00

    Just unwrapped a brand-new PC? Security pros share their secrets for making your system Internet-safe.
    A common misconception is that a shiny new computer is more or less secure because it hasn't yet been exposed to the Internet's sinister underbelly. But the truth is, these machines come out of the box needing scores of patches, some basic security software downloads and the disabling or replacing of items security pros don't typically trust.
  • +

    Facebook simplifies privacy settings, calls them too complex 02 July, 2009 05:48:00

    The social-networking site is also getting ready to let members share content with anyone on the Internet
    Facebook will simplify the way in which it offers privacy options to its users, as it gets ready to give its members for the first time the option to make the content they post on their profiles available to anyone on the Internet.
  • +

    DR a growing concern for A/NZ CIOs: Symantec 02 July, 2009 09:16:00

    Mission critical apps and cost of down-time major drivers
    CIOs in Australia and New Zealand are increasingly getting involved in the disaster recovery planning of their organisations, according to a new survey from Symantec.
Upcoming Industry Events
  • CIO SummitNSW - Sydney | 23/07/2009 | Hosted by CIO Magazine, IDC & the CIO Executive Council
Whitepaper

An Apple For Your Enterprise?

Whether it's a MacBook Pro or an iPhone, Apple is finding its way into the business world. Desktop Macs are moving into every department and data centers are rolling out Apple storage. They're everywhere. Are you ready?


CIO Industry Insight Podcast #4: Kerry Stratton, Managing Director of Healthcare, InterSystems
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email