CIO
HP's Supply Chain Lesson
If CIOs want to stop being held liable for hundreds of millions of dollars in losses for relatively small IT problems, they have to convince business leaders of the vastly increased risks that major enterprise software projects pose to businesses with high-volume supply chains.
Christopher Koch  23 February, 2005 12:37:24

Good project management isn't enough; CIOs need a worst-case contingency plan for the business

Reader ROI

  • How minor glitches in HP's ERP rollout snowballed into a $US160 million disaster
  • The limitations of IT project management to address business problems stemming from project snafus
  • Why business contingency plans are necessary for enterprise IT projects

It goes against human nature to always expect the worst. But with IT projects, pessimism - otherwise known as contingency planning - is the only way to keep small technology problems from becoming full-blown business disasters.

Too bad no one can bring themselves to do enough of it.

Christina Hanger had little reason to be pessimistic in May 2004, when she was moving one of Hewlett-Packard's biggest North American divisions onto a centralized ERP system from SAP. As the leader of an IT consolidation project rooted in HP's acquisition of Compaq two years earlier, Hanger, HP's senior vice president of Americas operations and IT, had an unbroken record of success migrating five product groups within the two former companies onto one of two SAP systems.

Hanger had every reason to believe that the sixth would go well too. Even so, she knew to be prepared for problems. At approximately $US7.5 billion in annual revenue, the division involved with this latest project, Industry Standard Servers (ISS), is much larger than any of the others that Hanger had migrated to SAP to that point. So Hanger took the contingency plan that her team had developed for the other five migrations and adjusted it to accommodate the ISS division's larger sales volume. She planned for three weeks of IT snafus, mostly focused on what might happen as a result of tweaking a legacy order-entry system to work with the new SAP system. The contingency plan addressed business impacts too. HP banked three weeks' worth of extra servers and took over an empty portion of an HP factory in Omaha to stand by for any overflow of orders that needed special configurations (for example, an unusual component or software combination) and could not be stockpiled ahead of time.

But the plan wasn't pessimistic enough.

Starting when the system went live at the beginning of June and continuing throughout the rest of the month, as many as 20 percent of customer orders for servers stopped dead in their tracks between the legacy order-entry system and the SAP system. As IT problems go, this wasn't too big: Some data modelling issues between the legacy system and the SAP system prevented the SAP system from processing some orders for customized products. These programming errors were fixed within four or five weeks. But Hanger and her business colleagues from the ISS division who were on the project steering committee never envisioned the degree to which these programming glitches would affect the business.

Orders began to backlog quickly and HP did not have enough manual workarounds to keep servers flowing fast enough to meet customer demand. Angry customers picked up the phone and called HP - or worse, arch-competitors Dell and IBM. In a commodity market such as servers, customer loyalty is built upon a company's ability to configure products to order and get them delivered on time. HP could do neither for much of the northern summer. In a third-quarter conference call on August 12, HP chairman and CEO Carly Fiorina pegged the financial impact at $US160 million: a $US120 million order backlog that resulted in $US40 million in lost revenue. That's more than the cost of the project itself, which AMR Research estimates to be $US30 million.

The headlines all claimed an IT disaster, but in fact, HP's disaster resulted from a few relatively small problems in IT that snowballed into a much bigger problem for the business: the inability to cope with the order backlog. This was a disaster that could have been prevented - not by trying to eliminate every possibility for error in a major IT system migration, which is virtually impossible, but by taking a much broader view of the impact that these projects can have on a company's supply chain.

CIOs don't run the supply chain in most companies, so they have trouble envisioning what will happen to sales if a critical system doesn't function as expected for a few days or weeks. Businesspeople, meanwhile, have trouble imagining an IT programming glitch getting past the walls of the data centre and causing hundreds of millions of dollars' worth of lost sales. The chasm between cause and effect is almost too vast to contemplate.

But if CIOs want to stop being held liable for hundreds of millions of dollars in losses for relatively small IT problems, they have to convince business leaders of the vastly increased risks that major enterprise software projects pose to businesses with high-volume supply chains. They must use that awareness to build - with full support and cooperation from the business - a business contingency plan for IT projects that is as robust as the project plans they create for the new software.

"The potential benefits to the supply chain are much bigger than the IT costs in projects like this," says Bill Swanton, vice president of research for AMR Research. "But the potential risk to the supply chain is also much bigger." If business contingency planning continues to play a secondary role to IT project management, the problem is only going to get worse as computer systems become more powerful, integration methods improve, and companies consolidate their critical business processes on fewer and fewer systems.

In retrospect, HP CIO and executive vice president of Global Operations Gilles Bouchard does not see the data modelling problems between the legacy and SAP systems as the source of the $US160 million impact. He focuses on HP's inability to keep pace with orders in the supply chain once the problems were discovered. "It was mostly capacity issues, material issues and factory issues," he says. "We had a series of small problems, none of which individually would have been too much to handle. But together they created the perfect storm."

Comments

Post new comment

Login or register to link comments to your user profile, or you may also post a comment without being logged in.
The content of this field is kept private and will not be shown publicly.
Enter the fully qualified URL, eg. http://www.example.com/
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

More information about formatting options

Syndicate content

HP Data Center Transformation solutions offer practical ways to overcome the energy and capacity limitations, operational vulnerabilities and technology constraints that can plague your data center. Choosing from a portfolio of solutions matched to your business needs, we can help you transform your data center into a business-driven, process-smart and future-ready asset.

Latest on Data Centre

  • +

    Inside Internode's data centre 05 June, 2009 14:39:00

    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
    Computerworld gets an exclusive behind the scenes look inside Internode's Adelaide data centre with network guru Mark Newton
  • +

    HP uses outside air, big fans, 12-foot raised floor to cool servers 03 June, 2009 07:44:00

    It's also cutting data center power use by painting server racks white
    Just off the North Sea coast in the United Kingdom, Hewlett-Packard Co.'s EDS unit has built a data center that largely relies on cold sea air to keep servers chilled and -- by doing so -- cut the center's cooling power needs in half.
  • +

    HP targets the cloud with new hardware 12 June, 2009 08:27:00

    HP offers complete cloud computing package for businesses
    HP has designed a new portfolio of hardware, software, and services, aimed at reducing costs and saving resource, particularly for businesses involved in Web 2.0, cloud and high-performance computing.
  • +

    Defence to spend $700m on ICT reform 05 June, 2009 11:13:00

    Strategic Reform Program report reveals only half of defence IT budget visible to CIO
    Less than half of the annual $1.2 billion spent by Defence on its ICT is visible to its chief information officer, Greg Farr, a new report has revealed.
  • +

    Inside Telstra's Virtualisation Strategy 11 May, 2009 14:12:00

    Need to cut infrastructure costs driving the strategy
    Telstra is increasingly turning to virtualisation as its core strategy to both manage the rising costs of, and growth in, its data centres, according the company’s CIO, John McInerney.
  • +

    Defence to Initiate ICT Reform Program, Expand CIO Role 05 May, 2009 11:56:00

    ERP rollout, data centre consolidation, single architecture all on the cards, according to the Department of Defence’s strategic policy white paper
    The Defence department has signaled a raft of changes to its approach to information technology under a new ICT reform program.

Free Resource Library

Data Centre Assessments

The First step to Optimising

Speeding business innovation

Removing barriers to growth, increasing agility and driving out costs

Assessments: Ammunition for Facts-Based Decision Making
by Richard L. Sawyer, Senior Principal, HP Critical Facilities Services
Download Podcast Download Transcript
 

CIO Summit The New World Order Opportunities and Challenges for CIOs

23rd July 2009
The Westin Sydney


A content-rich networking event where CIOs and senior executives collaborate on business and technology issues ranging from the impact of the economic downturn to the most pressing trends affecting IT in the enterprise.

Register Now

  • +

    New scam email uses Australian Federal Police to gain victims' trust 03 July, 2009 10:49:00

    Fake offers of free AFP monitoring service to stop "cybernetic attacks"
    Cyber criminals have changed tack in their ongoing scam campaign against banks, moving to the use of government agencies to gain the trust of unsuspecting email recipients.
  • +

    AFP hits $6 million identity fraud syndicate 03 July, 2009 08:25:00

    $500,000 of goods per week purchased with fake credit cards
    The Australian Federal Police (AFP) claims to have struck a major blow to a multi-million identity fraud syndicate.
  • +

    5 steps to secure a new PC 30 June, 2009 00:19:00

    Just unwrapped a brand-new PC? Security pros share their secrets for making your system Internet-safe.
    A common misconception is that a shiny new computer is more or less secure because it hasn't yet been exposed to the Internet's sinister underbelly. But the truth is, these machines come out of the box needing scores of patches, some basic security software downloads and the disabling or replacing of items security pros don't typically trust.
  • +

    Facebook simplifies privacy settings, calls them too complex 02 July, 2009 05:48:00

    The social-networking site is also getting ready to let members share content with anyone on the Internet
    Facebook will simplify the way in which it offers privacy options to its users, as it gets ready to give its members for the first time the option to make the content they post on their profiles available to anyone on the Internet.
  • +

    DR a growing concern for A/NZ CIOs: Symantec 02 July, 2009 09:16:00

    Mission critical apps and cost of down-time major drivers
    CIOs in Australia and New Zealand are increasingly getting involved in the disaster recovery planning of their organisations, according to a new survey from Symantec.
Upcoming Industry Events
  • CIO SummitNSW - Sydney | 23/07/2009 | Hosted by CIO Magazine, IDC & the CIO Executive Council
Whitepaper

Best Practices in Lifecycle Management

This white paper compares solutions from KACE, Altiris, LANDesk, and Microsoft. Read on for best practices, functional solution comparisons and cost comparisons. Determine overall value easily and quickly.


CIO Industry Insight Podcast #4: Kerry Stratton, Managing Director of Healthcare, InterSystems
Listen to the latest edition of CIO Live which is now available for download.
Listen to the podcast
Sign up to the CIO Live email